Project Schedule Management

Timing the Symphony of Construction: The Heart of Harmony Case Study

đź“… The Schedule Baseline

The Schedule Baseline is the approved version of the project schedule and serves as the primary standard against which project schedule performance is measured. For the "Heart of Harmony" Community Center Project, it is crucial for coordinating all 11 phases to meet the Grand Opening deadline.

Project Start Date

August 1, 2025

Grand Opening Milestone

January 15, 2028

High-Level Project Phases & Durations

Phase / Key Activity Start Date End Date Duration
Project Management & Initiation Aug 2025 Jan 2028 Ongoing
Design & Permitting (Milestone: Final Design Approval) Aug 1, 2025 Mar 31, 2026 8 months
Procurement & Contracts (Overlaps Design) Jan 1, 2026 May 31, 2026 5 months
Site Preparation & Foundation (Milestone: Groundbreaking Ceremony) Jun 1, 2026 Sep 30, 2026 4 months
Building Construction (Shell & Core) Oct 1, 2026 Jun 30, 2027 9 months
Building Interiors & Finishes Mar 1, 2027 Oct 31, 2027 8 months
MEP & IT Systems Installation Apr 1, 2027 Nov 30, 2027 8 months
Exterior Works & Landscaping Sep 1, 2027 Nov 30, 2027 3 months
Fit-Out & Furnishing Nov 1, 2027 Dec 15, 2027 1.5 months
Testing, Commissioning & Handover Dec 1, 2027 Dec 31, 2027 1 month
Project Closeout & Grand Opening Jan 1, 2028 Jan 15, 2028 2 weeks

This schedule baseline, often visualized in a Gantt Chart, shows significant overlapping phases (e.g., Procurement, Interiors, MEP) which indicates a fast-tracked or **"crashing"** approach to project execution—a high-risk strategy used to compress the schedule, which must be carefully managed. [Image of a typical Project Gantt Chart for construction]

⚙️ PMP Schedule Management Principles

As a Project Management Professional, understanding the processes behind this schedule is key:

  • Activity Definition: The detailed work packages from the WBS (Section 4.1.1) must be broken down into specific schedule activities.
  • Sequencing: Logical relationships (e.g., Finish-to-Start) define the order of work, ensuring the Foundation phase is completed before Shell & Core begins.
  • Duration Estimating: The duration estimates (e.g., 9 months for Shell & Core) were likely determined using expert judgment and analogous/parametric estimating methods.
  • Schedule Development: Techniques like the Critical Path Method (CPM) and resource leveling were used to calculate the overall project length and identify critical milestones.
  • Schedule Control: The use of **SPI** (Schedule Performance Index, as seen in your EVM calculator) will be the primary metric for monitoring and controlling the project's performance against this baseline.

Key PMP Focus:

For the PMP Exam, focus on the overlapping/crashing of Design/Procurement with Construction. This is a classic example of **Concurrent Engineering** used to meet the aggressive **January 15, 2028** deadline.