Skip to content
Comprehensive EVM Formulas Lesson | OPEX INSTITUTE

Earned Value Management (EVM) Formula Lesson

Essential Metrics for Project Performance Assessment | OPEX INSTITUTE

This lesson provides a comprehensive overview of the core metrics used in Earned Value Management (EVM). As a PMP, you know EVM is the standard methodology for assessing project performance by integrating scope, schedule, and cost. It uses a set of fundamental terms and powerful formulas to provide a clear, objective picture of project health.

🔑 Part 1: Foundational EVM Metrics (The Pillars)

These three monetary values are measured as of a specific status date in the project.

Metric Full Name / Old Terminology Definition
PV Planned Value / BCWS (Budgeted Cost of Work Scheduled) The budget for the work **planned** to be completed by the status date. *(How much work should have been done?)
EV Earned Value / BCWP (Budgeted Cost of Work Performed) The budget for the work **actually completed** by the status date. *(What is the value of the work done?)
AC Actual Cost / ACWP (Actual Cost of Work Performed) The money **spent** to achieve the work actually completed by the status date. *(How much money was spent?)

Note on Terminology:

  • BCWP (Budgeted Cost of Work Performed) is the older term for EV (Earned Value). They are the same.
  • ACWP (Actual Cost of Work Performed) is the older term for AC (Actual Cost). They are the same.

📈 Part 2: Performance Indices (Efficiency Ratios)

These ratios tell you the efficiency of the work performed. A value greater than 1.0 is considered favorable (good).

Index Formula What It Measures Interpretation
CPI $$\text{CPI} = \frac{EV}{AC}$$ Cost Efficiency If CPI > 1.0: Under budget. For every dollar spent, you earned more than one dollar's worth of value.
SPI $$\text{SPI} = \frac{EV}{PV}$$ Schedule Efficiency If SPI > 1.0: Ahead of schedule. You earned more value than you planned to by this date.

🔮 Part 3: Forecasting (The Future)

These metrics use current performance to forecast the final budget and time needed to complete the project.

Metric Formula (Most Common) What It Predicts Key Assumption
EAC $$\text{EAC} = \frac{\text{BAC}}{\text{CPI}}$$ Estimate At Completion: Predicted total cost. Default Assumption: Current cost performance ($\text{CPI}$) will continue for the rest of the project.
ETC $$\text{ETC} = \text{EAC} - \text{AC}$$ Estimate To Complete: Remaining cost needed. Directly related to the calculated EAC.
BAC BAC Budget At Completion: Original, total approved budget. -

Alternative EAC Formulas (Scenario-Based)

It's critical for certification preparation to understand alternative EAC formulas based on different project realities:

Scenario 1: Variances are Non-Recurring

If you believe past variances were non-recurring and future work will meet the original budget (future $\text{CPI}=1.0$):

$$\text{EAC} = \text{AC} + (\text{BAC} - \text{EV})$$

Scenario 2: Both Cost and Schedule Influence Remaining Work

If you believe both cost and schedule performance will influence the remaining costs:

$$\text{EAC} = \text{AC} + \left[ \frac{\text{BAC} - \text{EV}}{\text{CPI} \times \text{SPI}} \right]$$

© OPEX INSTITUTE. Empowering Operational & Project Excellence.