Project Management Scheduling Assignment: HoHCC

Project Scheduling and Compression Assignment

The Heart of Harmony Community Center

Prepared for: Joe's Project Management Students

Scenario: The Grand Opening Dilemma

Project: Heart of Harmony Community Center (HoHCC) Construction
Project Manager: Joe
Start Date: Friday, August 1, 2025 (Working Day 1)

Mandatory Milestone (Grand Opening): Monday, January 15, 2028

This is a non-negotiable hard deadline set by La Fondation Lumière. Your analysis must confirm if this date can be met.

Project Triple Constraint Priority (Accept, Enhance, Constraint):

  • Time: Constraint (The Grand Opening date must be met.)
  • Scope: Constraint (The facility's defined features and quality must be maintained.)
  • Cost: Accept (There is flexibility in the budget to absorb compression costs.)

The goal is to meet the Time and Scope Constraints while optimizing the Cost (Accept).

As the newly appointed Project Manager, you have inherited the project schedule data below. Your primary task is to establish the baseline schedule and determine if the current plan can meet the mandatory Grand Opening deadline. You must then propose a recovery strategy.

Assignment Objective & Instructions

Objective: Use the provided network data to analyze the schedule, identify the Critical Path, calculate the schedule variance against the target milestone, and recommend a strategy for schedule compression.

Part 1: Schedule Network Analysis (40 Points)

  1. Network Diagram: Draw the complete Precedence Diagramming Method (PDM) network diagram for the project activities listed in the data table below, showing all Finish-to-Start (FS) relationships. (The student must provide the PDM diagram in their submission).
  2. Forward Pass: Perform a Forward Pass analysis to calculate the Early Start (ES) and Early Finish (EF) dates (in Working Days) for every activity.
  3. Backward Pass: Perform a Backward Pass analysis to calculate the Late Finish (LF) and Late Start (LS) dates (in Working Days) for every activity.
  4. Float & Critical Path: Calculate the Total Float (TF) for every activity. Identify and list the activities that constitute the Critical Path (CP).

Part 2: Variance and Impact Analysis (30 Points)

  1. Baseline Finish Date: State the project's calculated Early Finish date (EF) for the Grand Opening Event (1.11.4-A) in both Working Days and the corresponding Calendar Date.
  2. Variance Calculation: Calculate the schedule variance in Working Days between the calculated finish date and the mandatory Grand Opening deadline (January 15, 2028).

    *(Note: The deadline of January 15, 2028, occurs on Working Day 619 of the project schedule.)*

  3. Impact Assessment: Explain the risks and impacts associated with missing a mandatory milestone of this magnitude. Discuss how this variance would affect the project's triple constraint (Scope, Cost, Time), referencing the priorities defined above.

Part 3: Schedule Compression Strategy (30 Points)

Based on your analysis in Part 2, propose a justified schedule compression strategy to meet the January 15, 2028 deadline.

  1. Strategy Selection: Recommend a combination of Fast Tracking and Crashing techniques. You must reduce the Critical Path duration by the variance calculated in Question 6.
  2. Implementation Plan (Compression):
    • Identify at least five (5) Critical Path activities that are suitable for duration reduction.
    • For each of the five selected activities, propose a new (compressed) duration and explicitly justify the technique used (e.g., *Crashing: adding a second shift* or *Fast Tracking: overlapping with predecessor*).
    • Prove that the sum of your proposed reductions meets or exceeds the required variance.
  3. Recalculation: Use your new compressed durations to perform a final Forward Pass calculation to confirm that the Grand Opening (1.11.4-A) now finishes on or before Working Day 619.

Project Schedule Network Data (Complete)

WBS Code Activity Name Duration (Days) Predecessor(s) Relationship Notes
1.1.1Project Planning & Initiation Completion60NoneFS
1.1.2Project Execution & Monitoring (Continuous Oversight)4001.1.1-AFS
1.1.4Project Closeout & Contract Reconciliation301.10.5-AFSFinal activity.
1.2.1Feasibility Studies & Site Analysis Completion60NoneFS
1.2.2Conceptual Design Development301.2.1-AFS
1.2.3Schematic Design Approval451.2.2-AFS
1.2.4Detailed Architectural & Engineering Design (Full Package)1201.2.3-AFSStructural, MEP, Civil, Landscape designs completed.
1.2.5-ASubmit Regulatory Approvals & Permitting Applications101.2.4-AFS
1.2.5-BAwait & Receive Building & Environmental Permits901.2.5-AFSLongest dependency/bottleneck for physical start.
1.2.6Tender Document Preparation (for Main Contractor)301.2.4-AFSCan run parallel to Permitting review (1.2.5-B).
1.3.1Main Contractor Selection & Contract Signing601.2.6-AFS
1.3.2-AOrder Long Lead MEP & IT Materials901.2.4-AFS
1.3.2-BProcure Finishes, Furniture, & Equipment601.2.4-AFS
1.4.1Geotechnical Investigation and Report Finalization151.2.1-AFS
1.4.2Site Clearing & Demolition (Ready for Grading)201.4.1-A, 1.2.5-BFSCrucial: Physical site work starts only after permits (1.2.5-B).
1.4.3Earthworks & Grading Completion301.4.2-AFS
1.4.4Foundation Construction & Curing751.4.3-A, 1.3.1-AFSRequires ground prep (1.4.3-A) and main contractor (1.3.1-A).
1.5.1Structural Framing (Steel & Concrete)901.4.4-AFS
1.5.2Roof Installation (Weathertight Roof Deck)301.5.1-AFS
1.5.3Exterior Walls & Cladding Installation601.5.2-AFS
1.5.4Windows & Doors Installation (Building Enclosure Complete)451.5.3-AFS
1.6.1Interior Framing & Drywall Installation451.5.4-AFS
1.6.2Flooring Installation (Main Areas)301.6.1-AFS
1.6.3Ceiling Installation301.6.1-AFS
1.6.4Interior Painting & Finishes201.6.2-A, 1.6.3-AFS
1.6.5Millwork & Cabinetry Installation301.6.4-AFS
1.6.6Restroom & Kitchen Fixture Installation151.6.5-A, 1.7.2-AFS
1.7.1-AElectrical System Rough-in601.5.4-A, 1.3.2-AFS
1.7.2-APlumbing System Rough-in451.5.4-A, 1.3.2-AFS
1.7.3-AHVAC System Installation (Ductwork, Units)751.5.4-A, 1.3.2-AFS
1.7.4-AFire Suppression System Installation251.7.2-AFS
1.7.6-AIT Infrastructure Installation (Cabling, Network)201.7.1-AFS
1.7.5-ASecurity System Installation151.7.6-AFS
1.8.1Parking Lot & Walkways Construction451.4.2-AFS
1.8.3Outdoor Lighting Installation101.7.1-A, 1.8.1-AFS
1.8.4Landscaping & Irrigation System Installation301.8.1-AFS
1.8.5Site Signage Installation51.8.4-AFS
1.9.1Main Hall & Room Furnishing Placement201.6.6-A, 1.3.2-BFS
1.9.4Kitchen Equipment Installation101.6.6-AFS
1.10.1System Testing & Debugging (MEP, IT, Security)151.7.5-A, 1.7.4-A, 1.7.3-AFS
1.10.2Building Commissioning & Punch List Creation101.9.1-A, 1.10.1-AFS
1.10.3Punch List Completion151.10.2-AFS
1.10.4Regulatory Handover & Occupancy Permit Receipt71.10.3-AFS
1.10.5Facility Management Training & Documentation Handover51.10.4-AFS
1.11.4Grand Opening Event Execution31.10.4-AFSMANDATORY FINISH (Day 619).